Construction Update – Dec. 4, 2012
Posted 12/04/2012 11:45 AM
The foundation work for the athletic field and parking complex project is now 65% complete. Crews worked all summer to excavate the site, put in earth retention systems and prepare the site for the building. In total, 65,000 cubic yards of dirt were removed from the site. (That’s 5,500 dump truck loads!)
Pile driving will wrap up next week, and soon the building will come to life. Crews are busy erecting the foundation wall forms, and in just a few days they’ll start pouring concrete for the foundation walls. They’ve already completed a 4-foot concrete foundation around the perimeter.
Toward the end of December, the precast concrete pieces of the structure will be delivered and crews will start setting the pieces in place.