Originally published September 18, 2012

The construction crew is in the final stages of installing the earth retention system at the athletic field/parking complex site. A layer of rock has been spread throughout the site. Because the base of the building will be so deep into the ground, the rock is needed as a drainage layer. This will ensure water doesn't enter the building once it’s built. At the end of September, the crew will start putting in the footings and foundation for the building.