Originally published April 12, 2013

We are now 60 percent finished with the installation of the precast concrete for the athletic field and parking complex, and expect to finish this work in about a month if the weather clears up. Not much has happened this week, as it has been raining non-stop. Work on the precast concrete began on the southern end of the facility and is moving north. The brick façade is also being installed, making the facility look like an extension of the Kern Center.

We expect to begin installing the athletic field in late June and the City of Milwaukee is scheduled to begin extending Market Street north from Knapp St. in mid-July.