Demolition activities to begin for Engineering Innovation Center
Beginning Sept. 18, 2025, demolition activities will begin on the north sides of the existing Fred F. Loock Engineering Center and Allen-Bradley Hall of Science in preparation for construction of the Robert D. Kern Engineering Center. Here are the areas of these buildings that will be most significantly impacted.
| Significantly Impacted Rooms | |
|---|---|
| Floor 1 | Fluid Power Institute Suite (Rooms S-139, S-139A, S-139B, S-141, S-142, S-144, S-146) |
| Floor 2 | Physics Suite (Rooms S-232, S-233, S-234, S-235, S-236, S-237), Rooms S-243, S-244, S-245, S-246, S-247 |
| Anticipated Durations | |
|---|---|
| Interior Wall Demolition (Floors G, 1 and 2) | 21 Days (3 Weeks) |
| Mass Demolition of North Side of Buildings | 30 Days (4 Weeks) |
| Exterior Demolition of Patio | 21 Days (3 Weeks) |